Walnut Grove – Project Update

Site works for Walnut Grove is coming along well.

This is what has happened since our last project update.

  • Topsoil stripping has been completed.

  • Plumbing and drainage works are underway.

  • Stormwater tanks installed end of May. 

  • Site pegging has been completed.

  • Pre-start selections and electrical drawings have been completed.

  • Western Power and NBN works have commenced.   

  • Due to sales success, Walnut Grove will be developed in 2 phases (instead of 3). Phase 1 is expected to be completed in mid 2017. Walnut Grove is expected to be fully completed by mid 2018. 

  • For more information one Walnut Grove, visit the project website www.mywalnutgrove.com